Center for Engineering and Planning — CEP

Projects / Renewable Energy

Design of PV Solar System for Al Qarara Water Tank – Khan Younis

Client / financing
American Near East Refugee Aid (ANERA) Financed through United States Agency for International Development (USAID)
Location
Palestine
Dates
2016
Renewable EnergyWater Supply, Transmission and DistributionElectrical Power Supply, Transmission and Distribution

Project Overview

This project involved the design, preparation of tender documents, and construction supervision for the development of a 3000 m³ water tank, booster station, 7.0 km water carrier lines, and other site facilities. The project also included the design of a PV solar system to power the lighting network and other light electrical loads across the project site.

Role of CEP in the project

Design of Solar System: The office designed a PV solar system to meet the energy needs of the lighting network and other electrical loads for the water tank and associated infrastructure.

Preparation of Tender Documents: Detailed tender documents for the solar system were developed, ensuring they aligned with the project’s specifications and requirements.

Construction Supervision: CEP provided oversight during construction to ensure that the solar system was installed according to design specifications and integrated seamlessly with the infrastructure.