Center for Engineering and Planning — CEP

Projects / Renewable Energy

Design of PV Solar System for Al Fukhari Water Tank – Khan Younis

Client / financing
American Near East Refugee Aid (ANERA) Financed through United States Agency for International Development (USAID)
Location
Palestine
Dates
2016–2018
Renewable EnergyWater Supply, Transmission and DistributionElectrical Power Supply, Transmission and Distribution

Project Overview

This project involved the design, preparation of tender documents, and construction supervision for the development of a 2000 m³ water tank, booster station, 3.5 km water carrier lines, and other site facilities. Additionally, the project included the design of a PV solar system to power the lighting network and other light loads at the project site.

Role of CEP in the project

Design of Solar System: The office designed a PV solar system to meet the energy requirements for lighting and other low-power systems at the project site.

Preparation of Tender Documents: Detailed documents were prepared for the installation of the solar system as part of the overall water infrastructure project.

Construction Supervision: CEP provided oversight during the construction phase to ensure the solar system was properly implemented and integrated into the project.